Report from the developer @rubicon.holding on the construction works performed in Kyivskyi Residential Complex in September.
3PC 1+2 sections
- We continue to finish and insulate the facade of the house.
- In the 2nd section, plastering works are underway in the apartments and common areas.
- In the 1st section, we have begun work on the installation of cement-sand screeds.
- We are installing the internal gas supply system (apartment by apartment).
- We continue to lay electrical networks in the 2nd section.
2PC 3+4+5 sections
- Works on laying the external and internal walls of the 4th and 5th sections of the 7th floor are in progress.
- The construction of the external and internal walls of the 7th floor of the 3rd section has been completed.
- We have completed the installation of floor slabs on the 6th floor.
- We are completing the concreting of the monolithic floor sections of the 4th and 5th sections of the 6th floor.
1PC 6+7 sections
- We have completed the waterproofing of the basement walls of the 6th and 7th sections.
- We have completed the masonry of the interior walls of the 6th and 7th sections of the 1st floor.
- Completed work on the laying of external and internal walls of the 6th section of the 2nd floor.
- Preparatory work is underway to arrange a monolithic reinforced concrete belt.