Report from the developer on the construction works performed in the residential complex Novi Teremky as of 3.04.2025.
Stage III:
- The lifting mechanism on the 10th house has been installed. Installation of the lifting mechanism for the 11th house is in progress.
- All the necessary materials for electrical wiring have been delivered. Installation works on the 1st to 6th floors have been completed, and work has begun on the 7th floor of the 10th building.
- Materials for the installation of cold and hot water supply and heating have been delivered. Work has begun on the 4th floor of the 10th building.
- Necessary materials for facade works were delivered, as well as 5 facade cradles, 3 of which have already been installed. The existing insulation was inspected. Facade works on building No. 10 have begun.
- Roofing works are ongoing. The 1st layer of waterproofing has been completed on the stylobate, and the 2nd layer is being installed.
- All the necessary materials have been lifted to the roofs of houses 10 and 11. Insulation and concrete screed have been installed on building No. 10. Insulation and concrete screed have been completed on the 11th house.
- Installation of lightning protection system belts and downpipes on houses 10 and 11 has been completed.
Short-term plans:
In April, windows for the 3rd phase will be delivered and their installation will begin.
Ventilation equipment will also be delivered in April.
The construction of a transformer substation for the needs of the 3rd and 4th phases will begin.