Report from the developer on the construction work carried out at the ‘Novi Teremky’ residential complex as at August 2026.
Phase 3
- Painting of the external walls has been completed on floors 2 to 15 inclusive.
- Work in the lift machine rooms and lift shafts has been completed, and the lift lobbies have been finished. Commissioning work is ongoing;
- Installation of electrical distribution boards is ongoing;
- Facade work is nearing completion;
- Painting of the stairwells from the 2nd to the 15th floors has been completed;
- The fire-extinguishing system is 95% complete;
- Landscaping has begun. Site planning and road formation are underway;
- The heat distribution unit, pumping stations and boiler room are ready for commissioning;
- Waterproofing of the basement has been completed.
Phase 4
- Concrete works are ongoing; two floors were poured during the reporting period;
- Installation of ventilation units is ongoing;
- We are continuing with the brickwork;
- Installation of the second crane for buildings 12–14 has been completed. Additional formwork kits have been purchased;
- Preparatory work is underway to reinforce the structures of Section 12.
Phases 5–7
- Work has been completed on constructing the embankment for the existing excavation (lake);
- Electricity has been connected to the site;
- A pump and auxiliary materials for water extraction have been purchased.