logo
  • Company
    • About Us
    • Social responsibility
  • Projects
  • Directions
  • News
  • Contact Us
+38 066 7778030
  • en
  • ua
  1. Home
  2. News
  3. Progress of construction at the ‘Novi Teremky’ residential complex

News

FEEDBACK

Progress of construction at the ‘Novi Teremky’ residential complex

Report from the developer on the construction work carried out at the ‘Novi Teremky’ residential complex as at August 2026.

Phase 3

  • Painting of the external walls has been completed on floors 2 to 15 inclusive.
  • Work in the lift machine rooms and lift shafts has been completed, and the lift lobbies have been finished. Commissioning work is ongoing;
  • Installation of electrical distribution boards is ongoing;
  • Facade work is nearing completion;
  • Painting of the stairwells from the 2nd to the 15th floors has been completed;
  • The fire-extinguishing system is 95% complete;
  • Landscaping has begun. Site planning and road formation are underway;
  • The heat distribution unit, pumping stations and boiler room are ready for commissioning;
  • Waterproofing of the basement has been completed.

Phase 4

  • Concrete works are ongoing; two floors were poured during the reporting period;
  • Installation of ventilation units is ongoing;
  • We are continuing with the brickwork;
  • Installation of the second crane for buildings 12–14 has been completed. Additional formwork kits have been purchased;
  • Preparatory work is underway to reinforce the structures of Section 12.

Phases 5–7

  • Work has been completed on constructing the embankment for the existing excavation (lake);
  • Electricity has been connected to the site;
  • A pump and auxiliary materials for water extraction have been purchased.

Rubicon Holding
  • +38 066 7778030
  • KropyvnytskyiSt. Chikalenko 1A, office 425
  • office@gc-rubicon.com.ua
  • ©Rubicon Holding2026

  • Ноme
  • Company
  • Projects
  • Directions
  • News
  • Contact Us
Powered By Blade.MSP ® from BrainTEC ™