Interim report from Rubicon Holding on the work completed in the Kovalevsky residential complex as of 30 November 2025.
Section 5
- Work is continuing on the installation of window structures and balcony blocks.
- The monolithic belt on the 10th floor has been completed, with 95% of the floor slabs in place.
- We are continuing to install the parapets on the 10th floor.
Section 6
- Preparation of the second floor for the floor slab is complete.