Construction progress in the Novi Teremky residential complex

Detailed report from the developer on construction work completed in August in the Novi Teremky residential complex

Phase 3:

Building 10:

  • Work on connecting electricity and utilities to the apartments has been completed.
  • Bricklaying work has been completed.
  • Ceramic tiles have been delivered.

Building 11:

  • The connection of electricity and utilities to the apartments is being completed, with only the first floor remaining.
  • Bricklaying work is continuing on the top floor.
  • Ceramic tiles have been delivered.
  • Facade work and window installation are continuing.

Phase 4:

  • Work is continuing on cutting openings for prefabricated staircases and landings and their installation.
  • We are continuing to carry out preparatory work for the installation of monolithic staircases.
  • Work is continuing on the installation of reinforced concrete blocks.
  • Grouting of joints and welding of prefabricated ventilation block supports is ongoing.
  • We are working on cutting (finishing) openings for prefabricated ventilation blocks.
  • Manufacturing of metal frames for vertical and horizontal elements of monolithic frames is ongoing.
  • Work continues on welding vertical frame elements when installing them at design marks.
  • We are continuing the process of dismantling formwork and dismantling frames for monolithic work (door openings).
  • Preparation and installation of scaffolding and platforms for monolithic work in lift shafts is continuing.
  • The installation of vertical elements of the monolithic frame continues.

A set of geodetic survey works has been completed:

Preparatory work for marking out section 16:
  • Affixing 4 reference marks to the cornices of buildings.
  • Coordination of marks into a single coordinate system.
  • Surveying of vertical reference points on the 7th floor.
  • Overlaying the survey on the vertical drawing of a typical floor.
  • Analysis and coordination of the vertical drawing together with the marks based on the survey data.
  • Marking of the vertical at elevation +34.420.
  • Transfer of the elevation benchmark +1.500 from the top of the floor slab.

Preparatory work for marking section 17:

  • Surveying of vertical reference points on the 7th floor.
  • Overlaying the survey on the vertical drawing of a typical floor.
  • Analysis and coordination of the vertical drawing together with marks based on the survey data.

Additionally:

  • Marking of the top of the staircase landing of section 16 between the 1st and 3rd floors.
  • Marking of the contours of the ventilation shafts of section 17 on the 3rd floor.
  • Marking of the elevator and staircase of section 17 at elevation +28.420.

5–7 phase:

Due to the fact that the previous developer did not obtain a permit to start construction, new project documentation is being developed, already referring to the current building codes.

  • The project for the first building of the phase has been sent for expert review.
  • After receiving the expert report, the process of obtaining permission to start construction will begin.
  • The development of the overall concept of the complex is being completed. We expect to receive a presentation of the project in the near future.

After obtaining a building permit, there will be grounds for signing contracts with investors in phases 5-7 of the Novi Teremky residential complex.

Rubicon Holding
  • +38 066 7778030
  • KropyvnytskyiSt. Chikalenko 1A, office 425
  • office@gc-rubicon.com.ua
  • ©Rubicon Holding2025

  • Ноme
  • Company
  • Projects
  • Directions
  • News
  • Contact Us
Powered By Blade.MSP ® from BrainTEC ™