Report from the developer on construction work completed in the Novi Teremky residential complex in July 2025.
Third phase – buildings No. 10-11:
- Roofing work completed;
- 90% of windows installed;
- Work on insulating the buildings is continuing;
- Work on finishing the common areas is continuing;
- Work on connecting utilities to the apartments (electricity, heating, water supply) is continuing.
Fourth phase – buildings No. 12-18:
- Installation of reinforced concrete structures (staircases, ventilation units) has begun;
- Bricklaying of walls has begun;
- Work on the construction of monolithic frames for the upper floors has begun.