Report from the developer on the construction works performed in Novi Teremky as of June 2025.
Stage 3:
- Installation of partition walls in building 10 is in progress.
- Electrical installation works are underway in building 10, 3 floors remain.
- Plumbing works are underway in house No. 10, 4 floors remain.
- We continue to perform facade works on houses 10 and 11.
- The roofing of the 10th house has been completed, and works on the 11th house are in progress.
- Screed installation works on the 10th building are nearing completion, with 4 floors remaining.
- Plastering works are underway at the 10th building.
- All the windows at the 10th building have been installed, and materials for the revision of the windows installed by the previous developer have been delivered.
- Works are underway to lay fibre-optic cable (Internet) in the houses of the 3rd stage.
- A contract was signed for the supply and installation of lifts in buildings 10 and 11.
Stage 4:
- The report on the inspection of the load-bearing structures of the buildings of the 4th stage was received, and the development of a model of measures to strengthen the structures is underway.
- A set of formwork for monolithic works was ordered and paid for;
- Concrete products for houses 14, 15, 16 have been ordered and paid for.
- Bricks have been delivered and partially distributed on the floors of buildings 14-16.