Report from the developer on the construction works performed in Novi Teremky Residential Complex as of 18.04.2025.
Stage 3:
- Installation of the lifting mechanism for the house No. 11 has begun.
- Electricity wiring in the house No. 10 is in progress. As of 18.04.2025, we have moved to the 12th floor of the 10th building (works 1 to 12 have been completed).
- Works on installation of water supply and heating system in the building No. 10 are in progress.
- Facade works on the building No. 10 continue. Two teams are working on the facade and one on the roof (finishing the parapets). Two more teams are expected to start working on 22 April.
- Work continues on the roof of the 3rd stage.
- Installation of metal-plastic windows in building No. 10 has begun. As of 18.04, 70% of the windows have been delivered, with the rest expected by the end of April. The estimated completion date is mid-May.
- Metal enclosing structures for houses 10 and 11 have been ordered and advanced. Installation works in the 10th building will start on 25 April.
- A supplier of lift equipment has been selected. Reliable and energy-efficient lifts made in Turkey were ordered.
- Ventilation equipment for buildings 10-11 was delivered. Preparations for installation have begun.
Stage 4
- All the necessary additional measurements and tests were taken - water was pumped out of the basements, all floors/all pylons were ‘rung’ and additionally checked, and the foundation was checked.
- Within 3 weeks, we expect a ready-made 3D model and an official decision on the completion of calculations for strengthening the structures of the 4th stage.
- We have completed the selection of the necessary mechanisms for monolithic works and expect to sign contracts in the near future.
- The crane is scheduled to be installed in May and monolithic works are expected to start.
- We continue to prepare the construction site.