Report from the developer on the completed construction works in Kyivskyi residential complex as of 15.05.2025

3LC 1+2 sections

  • We continue to work on the arrangement of the internal gas supply system in the second section.
  • Ceramic tiles are being laid in the common areas of the entrance groups of the first and second sections.
  • We continue interior finishing works in the first and second sections.
  • We have completed the installation of apartment water meters.
  • We have completed the installation of plumbing inspection hatches in the first section and are continuing to install them in the second section.
  • We are also working on the facade.

2LC 3+4+5 sections

  • Installation of floor slabs on the eighth floor has begun.
  • We are manufacturing reinforcing cages and installing formwork for monolithic floor sections.
  • Concreting and installation of monolithic reinforced concrete balconies in section 5 has been completed.

1LC 6+7 sections

  • Installation of floor slabs on the second floor of the 6th and 7th sections has been completed.
  • We are completing the laying of load-bearing walls on the 3rd floor of the sixth and seventh sections.
  • Installation of staircases and landings on the 3rd floor of the sixth and seventh sections.

Rubicon Holding
  • +38 066 7778030
  • KropyvnytskyiSt. Chikalenko 1A, office 425