Interim report from the developer on the work completed in the Kovalivvsky residential complex as of 30 October 2025
Section 5
- Completion of partition walls in storage rooms on floors 8–9;
- Reinforced belt prepared for pouring the final part of the floor slab;
- Approximately 70% of the 10th floor area covered;
- Installation of balcony blocks and window structures commenced.
Section 6
- Floor slabs damaged during downtime completely dismantled;
- All necessary slabs for the 2nd floor have been ordered;
- The masonry of the partitions necessary for the construction of the 2nd floor has been completed;
- The masonry of the storage rooms on the ground floor has been completed;
- The masonry of the lift shaft has begun.