Report from the developer, Rubicon Holding, on the work completed at the ‘Parkovy Kvartal’ residential complex as at August 2026.
Building 7:
- work on the foundation has been completed;
- work is ongoing on the installation of FBS foundation blocks;
- work is being carried out on the waterproofing of the external part of the foundation.
Building 6:
- we are carrying out the concreting of monolithic sections and the 4th-floor balconies;
- the installation of reinforcement cages and formwork for the monolithic sections and the 4th-floor balconies is ongoing;
- bricklaying of the 5th-floor walls is continuing.
Building 5:
- facade work has been completed;
- work is underway on landscaping the surrounding area;
- the installation of utilities in the basement (K1, K2 and air conditioning units) has been completed;
- water meters have been installed in the entrance halls;
- the installation of window flashings has been completed;
- we are continuing to process the necessary permits for connecting the building to the external water supply, sewerage and electricity networks.