Report from the developer on construction work completed at the ‘Novi Teremky’ residential complex as of early May 2026.
Phase 3 (Buildings 10–11)
- Lift installation is continuing;
- The laying of ceramic tiles in the communal areas is nearing completion;
- Installation of the pumping station and individual heating substation in Building 11 is ongoing;
- Work continues on the installation of the storm drainage system and the boiler room;
- Installation of the fire alarm system is ongoing;
- Door installation is nearing completion.
Phase 4
- Concrete works are ongoing on the 15th floor in sections 17–18;
- Bricklaying continues on section 16.