Report from the developer on construction work completed at the ‘Kyivskyi’ residential complex as at 15 July 2026.
3PC, Sections 1+2
- Work on landscaping the area around the buildings has been completed;
- Street lighting has been installed;
- Lift equipment has been installed in the first and second sections.
- We have received the certificate of readiness for the building to be put into operation.
2PC Sections 3, 4 and 5
- We are continuing work on the insulation and cladding of the façade;
- We are carrying out work on the waterproofing of the building’s roof;
- We are continuing work on the bricklaying of internal partition walls between rooms and flats;
- We are completing work on the installation of the flue system.
1PC, Sections 6 and 7
- We have completed the installation of the monolithic reinforced concrete ring beam on the 5th floor of Sections 6 and 7;
- We have completed the bricklaying of the external and internal walls on the 5th floor of Section 6;
- We are finalising the installation of floor slabs on the 4th floor of Section 6;
- We are carrying out bricklaying work on the external and internal walls of the 6th floor of Section 7.