logo
  • Company
    • About Us
    • Social responsibility
  • Projects
  • Directions
  • News
  • Contact Us
+38 066 7778030
  • en
  • ua
  1. Home
  2. News
  3. Construction progress at the ‘Kyivskyi’ residential complex

News

FEEDBACK

Construction progress at the ‘Kyivskyi’ residential complex

Developer’s report on construction work completed at the ‘Kyivskyi’ residential complex as of 18 April 2026

3PK Sections 1 and 2

  • The installation of the internal gas supply system and gas meters throughout the building has been completed.
  • Work has been carried out to install individual gas boilers in sections 1 and 2.
  • The installation of doors in the storage rooms has been completed.
  • We are currently working on the landscaping of the surrounding area.
  • Work has begun on the installation of lift equipment in Section 1.
  • We are completing the facade work on the parapet walls of the roof and the chimneys.

2PC Sections 3, 4 and 5

  • We are continuing work on the facade of Sections 3 and 4.
  • The installation of metal-plastic door and window frames is 90% complete.
  • We are continuing the installation of metal-plastic door and window frames in the commercial premises.
  • We are continuing work on the bricklaying of internal partition walls between rooms and flats.

1PC Sections 6 and 7

  • We have completed the installation of floor slabs on the 4th floor of Sections 6 and 7.
  • We have carried out concrete works on the monolithic sections of the floor and balconies on the 4th floor of Sections 6 and 7.
  • We have completed the bricklaying of the external and internal load-bearing walls on the 5th floor of Section 7.
  • We are continuing the bricklaying of the external and internal walls on the 5th floor of Section 6.
  • We are carrying out concrete works on the monolithic reinforced concrete ring beam on the 5th floor of Section 7.
DTEK has completed work on the installation of external 0.4 kV power supply networks and has carried out work on the installation of additional equipment in the transformer substation for the buildings of the 4th phase of 3PC; 2PC and 1PC.

Kyivskyi Residential Complex #happinessbeginsathome

Rubicon Holding
  • +38 066 7778030
  • KropyvnytskyiSt. Chikalenko 1A, office 425
  • office@gc-rubicon.com.ua
  • ©Rubicon Holding2026

  • Ноme
  • Company
  • Projects
  • Directions
  • News
  • Contact Us
Powered By Blade.MSP ® from BrainTEC ™