Report on construction progress at the Kovalevsky residential complex, as of 01.10.2025

Section 5

  • Supply of materials: floor slabs, bricks, sand, rolled metal, and cement have been delivered and stored on site.
  • Partitions: inter-apartment and intra-apartment partitions have been built on 7 floors.
  • Balconies (fencing/preparation for glazing):

✔️brick fencing for 20 balconies has been completed;

✔️reinforcement of the fencing masonry has been completed in accordance with the project;

✔️preparatory work for the installation of balcony blocks and glazing has been completed.

  • Storage rooms (MZK):

✔️brick partition walls of storage rooms up to and including the 8th floor have been completed;

Section 6

  • Demolition: rows of silicate bricks and individual floor slabs damaged during downtime were demolished (with subsequent restoration of structural integrity).
  • Load-bearing structures: construction of load-bearing walls on the 2nd floor was completed.
  • Basement/plinth: masonry of storage room partitions on the plinth floor was completed.

Rubicon Holding
  • +38 066 7778030
  • KropyvnytskyiSt. Chikalenko 1A, office 425
  • office@gc-rubicon.com.ua
  • ©Rubicon Holding2025

  • Ноme
  • Company
  • Projects
  • Directions
  • News
  • Contact Us
Powered By Blade.MSP ® from BrainTEC ™