Construction progress at the Kovalivskyi residential complex as at early September 2026

Progress report on construction work at the ‘Kovalivskyi’ residential complex as at the beginning of September 2026.

The following work has been completed on the 3rd floor of Section 6:

  • brickwork for external and internal walls;
  • brickwork for the bathroom partitions on the 2nd and 3rd floors;
  • anti-corrosion protection of the masonry mesh;
  • construction of monolithic sections;
  • installation of floor slabs and two stairwell slabs;
  • installation of the landing.

In Section 5 (on the 2nd, 3rd, 4th, 10th and technical floors), the following work has been completed:

  • construction of internal partitions from aerated concrete blocks and tongue-and-groove blocks on the balconies (2nd, 3rd and 4th floors);
  • bricklaying of the technical floor walls and lift shaft walls;
  • construction of monolithic sections and concreting of monolithic beams on the technical floor;
  • installation of floor slabs on the technical floor;
  • preparation of the 10th-floor slab surface for the screed;
  • insulation of the 10th-floor slab with mineral wool and expanded polystyrene;
  • laying of a cement screed on the ground floor and on the 10th-floor slab;
  • cleaning of ventilation ducts.

VIDEO REVIEW

Rubicon Holding
  • +38 066 7778030
  • KropyvnytskyiSt. Chikalenko 1A, office 425
  • office@gc-rubicon.com.ua
  • ©Rubicon Holding2026

  • Ноme
  • Company
  • Projects
  • Directions
  • News
  • Contact Us
Powered By Blade.MSP ® from BrainTEC ™