Progress report on construction work at the ‘Kovalivskyi’ residential complex as of early May 2026.
Section 5
- The monolithic ring beam at the 10th-floor level has been partially completed, and formwork installation is ongoing. The parapet walls are being built.
- The balconies are already taking shape — approximately 80% of the railings have been welded.
- In parallel, work is continuing on drainage and the installation of storm sewers.
Section 6
- The erection of the 3rd-floor walls is continuing.
Construction work is proceeding according to schedule, thanks to the timely supply of the necessary materials for further construction.